Page 11 - Stack London Brochure
P. 11

PORTFOLIO Location
RAF Stanbridge Leighton Buzzard Beds LU7 4QT
Client
Catalyst Housing Group
Date
Live Project
Summary
Stack are providing an an experienced Construction Management team to to undertake the new build construction of 178 houses at at Stanbridge Leighton Buzzard for Catalyst Housing Group
The Stack team are responsible for managing and coordinating the design work providing all site preliminary items including welfare vertical and and horizontal distribution site management management skilled skilled and and and unskilled labour sub-contractor management management and and coordination The Stack commercial team are tendering negotiating preparing executing and administering the the the JCT Trade Contract packages required to deliver the the the project for the the the client Full site works are underway and and the first units were handed over February 2018 Contract Value
£27 00m
Contract Period
JCT Construction Management 2011 – 118 weeks